Phase 2

  • Establish perimeter fencing to works area
  • Parking area along the entrance road
  • Reduced level excavation under archaeological supervision
  • Duct trenching under archaeological supervision
  • Ducting to lamp posts, feeder pillars and barriers, including bases (unrestricted works)
  • Kerbs and edgings
  • Type 3 to parking bays
  • Grid paving, including gravel infill

Existing Car Park & House Frontage

  • Reduced level excavation under archaeological supervision
  • Duct trenching under archaeological supervision
  • Ducting to lamp post, feeder pillars and barriers including bases unrestricted works
  • Kerbs and edgings
  • Type 1 to all areas

Courtyard and Data/60’s Building Area

  • Path from the courtyard to the existing car park
  • No-dig section, including edgings, grid paving, infill, topsoil, making good and gravel

Courtyard

  • Reduced level excavation under archaeological supervision
  • Duct runs to area, access chambers, lamp posts, bases, etc.
  • Duct trenching under archaeological supervision
  • Unrestricted works
  • Kerbs and edgings
  • Type 1 to all areas