The project continues to progress well and remains on programme, with no delays anticipated.
Phase 2
- Establish perimeter fencing to works area
- Parking area along the entrance road
- Reduced level excavation under archaeological supervision
- Duct trenching under archaeological supervision
- Ducting to lamp posts, feeder pillars and barriers, including bases (unrestricted works)
- Kerbs and edgings
- Type 3 to parking bays
- Grid paving, including gravel infill
Existing Car Park & House Frontage
- Reduced level excavation under archaeological supervision
- Duct trenching under archaeological supervision
- Ducting to lamp post, feeder pillars and barriers including bases unrestricted works
- Kerbs and edgings
- Type 1 to all areas
Courtyard and Data/60’s Building Area
- Path from the courtyard to the existing car park
- No-dig section, including edgings, grid paving, infill, topsoil, making good and gravel
Courtyard
- Reduced level excavation under archaeological supervision
- Duct runs to area, access chambers, lamp posts, bases, etc.
- Duct trenching under archaeological supervision
- Unrestricted works
- Kerbs and edgings
- Type 1 to all areas