The project continues to progress well and remains on programme, with no delays currently anticipated.
Phase 1
- Street furniture and lamp posts including feeder pillar bases etc
- Install command posts etc
- Type 1, final grading to roads
- Surfacing including surface course
- Signage and white lining etc
- Remove perimeter fencing
- Completion inspection
New Tree Line Footpath
- Surfacing
Entrance Road
- Street furniture and lamp posts including feeder pillar bases etc
- Install command posts etc
- Surfacing
- Disconnection and removal of lamp posts
Exit Road
- Street furniture and posts including feeder pillar bases etc
- Install command posts etc
- Surfacing including road crossings
- Signage and white lining etc
Electrical and Data Works
- Install main cables to car park and entrance road
- Install main cable to tree lined path
- Install main cables to entrance road
- Install main cables to exit road, lv switch and fp1