Police HQ Car Park – Programme of Works (JULY 2026)

The project continues to progress well and remains on programme, with no delays currently anticipated.

Phase 1

  • Street furniture and lamp posts including feeder pillar bases etc
  • Install command posts etc
  • Type 1, final grading to roads
  • Surfacing including surface course
  • Signage and white lining etc
  • Remove perimeter fencing
  • Completion inspection

New Tree Line Footpath

  • Surfacing

Entrance Road

  • Street furniture and lamp posts including feeder pillar bases etc
  • Install command posts etc
  • Surfacing
  • Disconnection and removal of lamp posts

Exit Road

  • Street furniture and posts including feeder pillar bases etc
  • Install command posts etc
  • Surfacing including road crossings
  • Signage and white lining etc

Electrical and Data Works

  • Install main cables to car park and entrance road
  • Install main cable to tree lined path
  • Install main cables to entrance road
  • Install main cables to exit road, lv switch and fp1